Herrenknecht AR Logo

All Around #7

EVERYTHING FLOWS

 

International championship alliance completes world class metro tunnel project in Doha in record time.

111 KILOMETER IN 26 MONTHS – WORLD RECORD MISSION COMPLETED

Out of nowhere, almost unnoticed underground, an epoch-making structure is created in Doha. With a total of 111 kilometers a top-class metro tunnel project. The protagonists of the prestige project: Qatar Rail, four international construction joint ventures and 21 EPB Shields from Herrenknecht.

 

Together they realize a highly complex, extremely ambitious undertaking that seeks its equal worldwide. After 26 months of tightly directed tunnelling flow, it was successfully completed with the final breakthrough on September 25, 2016.

FLOW³

MULTITASKING IN PERFECTION

 

Precise, on schedule, synchronous: 21 tunnel boring machines were needed to drive the mega project forward on three metro lines. Under the direction of Qatar Rail, four international joint ventures delivered an unprecedented tunnelling rally under enormous time pressure with the highest standards of safety.

 

Follow the tunnel borers on their journey through time. Witness a new benchmark on an international scale: Flow³.

Timeline TBM S-846 TBM S-865 TBM S-867 TBM S-868 TBM S-847 TBM S-860 TBM S-862 TBM S-866 TBM S-863 TBM S-920 TBM S-921 TBM S-922 TBM S-923 TBM S-924 TBM S-925 TBM S-864 TBM S-861 TBM S-849 TBM S-848 TBM S-844 TBM S-845 08.01.2016 Intermediate Breakthrough 30.12.2015 Intermediate Breakthrough 24.02.2016 Intermediate Breakthrough 07.03.2015 Intermediate Breakthrough 08.02.2016 Intermediate Breakthrough 29.02.2016 Intermediate Breakthrough 18.02.2016 Intermediate Breakthrough 13.02.2016 Intermediate Breakthrough 28.02.2016 Intermediate Breakthrough 02.02.2016 Intermediate Breakthrough 14.11.2015 Intermediate Breakthrough 08.11.2015 Intermediate Breakthrough 10.11.2015 Intermediate Breakthrough 22.11.2016 Intermediate Breakthrough 26.10.2015 Intermediate Breakthrough 16.11.2015 Intermediate Breakthrough 28.10.2015 Intermediate Breakthrough 25.10.2015 Intermediate Breakthrough 10.09.2015 Intermediate Breakthrough 10.10.2015 Intermediate Breakthrough 13.10.2015 Intermediate Breakthrough 10.10.2015 Intermediate Breakthrough 30.08.2015 Intermediate Breakthrough 30.09.2015 Intermediate Breakthrough 29.08.2015 Intermediate Breakthrough 21.07.2015 Intermediate Breakthrough 26.07.2015 Intermediate Breakthrough 05.09.2015 Intermediate Breakthrough 21.09.2015 Intermediate Breakthrough 04.10.2015 Intermediate Breakthrough 27.09.2015 Intermediate Breakthrough 14.10.2015 Intermediate Breakthrough 25.10.2015 Intermediate Breakthrough 02.10.2015 Intermediate Breakthrough 06.10.15 Intermediate Breakthrough 30.07.2015 Intermediate Breakthrough 03.06.2015 Intermediate Breakthrough 24.06.2015 Intermediate Breakthrough 11.06.2015 Intermediate Breakthrough 23.06.2015 Intermediate Breakthrough 23.07.2015 Intermediate Breakthrough 31.05.2016 Intermediate Breakthrough 31.01.2015 Intermediate Breakthrough 04.04.2015 Intermediate Breakthrough 17.01.2015 Intermediate Breakthrough 15.04.2015 Intermediate Breakthrough 26.04.2015 Intermediate Breakthrough 11.04.2015 Intermediate Breakthrough 14.04.2015 Intermediate Breakthrough 25.03.2015 Intermediate Breakthrough 09.04.2015 Intermediate Breakthrough 16.06.2015 Intermediate Breakthrough 01.06.2015 Intermediate Breakthrough 07.02.2016, S-868 Final Breakthrough 12.12.2015, S-847 Final Breakthrough 20.03.2016, S-867 Final Breakthrough 12.03.2016, S-865 Final Breakthrough 31.07.2016, S-864 Final Breakthrough 11.07.2016, S-863 Final Breakthrough 08.06.2016, S-861 Final Breakthrough 01.05.2016, S-925 Final Breakthrough 11.05.2016, S-924 Final Breakthrough 11.05.2016, S-923 Final Breakthrough 12.05.2016, S-922 Final Breakthrough 10.09.2016, S-860 Final Breakthrough 29.02.2016, S-849 Final Breakthrough 27.02.2016, S-848 Final Breakthrough 12.12.2015, S-923 Final Breakthrough 28.11.2015, S-846 Final Breakthrough 29.03.2016, S-844 Final Breakthrough 27.03.2016, S-845 Final Breakthrough 04.05.2016, S-920 Final Breakthrough 19.05.2016, S-921 Final Breakthrough
Accumulated
tunnelling progress

The success in figures

PERFORMANCE PARADE

Maximum machine availability is the basis of peak performance. Together the project participants in Doha managed the feat of delivering an average overall availability of more than 97%.

 

Click through the detailed numbers of the individual TBMs.

 

97.2%

S-860 – Lehwaila (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

96.1

Total tunnelling length: 9,069 m

Maximum advance per week: 269 m

S-861 – Al Wakra (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

98.3

Total tunnelling length: 5,126 m

Maximum advance per week: 216 m

S-862 – Msheireb (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

97.6

Total tunnelling length: 9,130 m

Maximum advance per week: 250 m

S-863 – Doha (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

90.8

Total tunnelling length: 5,074 m

Maximum advance per week: 184 m

S-864 – Al Zubara (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

96.6

Total tunnelling length: 4,242 m

Maximum advance per week: 190 m

S-865 – Lebretha (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94.1

Total tunnelling length: 7,182 m

Maximum advance per week: 195 m

S-866 – Al Mayeda (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

93.9

Total tunnelling length: 4,157 m

Maximum advance per week: 209 m

S-867 – Al Khor (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94.1

Total tunnelling length: 7,223 m

Maximum advance per week: 209 m

S-868 – Al Bidda (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94

Total tunnelling length: 4,232 m

Maximum advance per week: 194 m

S-844 – Al Messila (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

96.7

Total tunnelling length: 6,141 m

Maximum advance per week: 210 m

S-845 – Al Sheehaniya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.8

Total tunnelling length: 6,150 m

Maximum advance per week: 213 m

S-846 – Al Rayyan (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.3

Total tunnelling length: 4,082 m

Maximum advance per week: 216 m

S-847 – Al Gharrafa (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

99

Total tunnelling length: 4,090 m

Maximum advance per week: 203 m

S-848 – Leatooriya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

99

Total tunnelling length: 6,454 m

Maximum advance per week: 232 m

S-849 – Lijmailiya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.8

Total tunnelling length: 6,466 m

Maximum advance per week: 283 m

S-920 – Sharq (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.3

Total tunnelling length: 4,371 m

Maximum advance per week: 177 m

S-921 – Lusail (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.1

Total tunnelling length: 4,382 m

Maximum advance per week: 195 m

S-922 – Al Sadd (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.5

Total tunnelling length: 3,557 m

Maximum advance per week: 266 m

S-923 – Al Sailiya (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

98.3

Total tunnelling length: 3,558 m

Maximum advance per week: 180 m

S-924 – Muaither (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.6

Total tunnelling length: 3,725 m

Maximum advance per week: 213 m

S-925 – Al Waab (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.9

Total tunnelling length: 3,728 m

Maximum advance per week: 201 m

THE PROJECT IN DETAIL

DOHA METRO

Qatar Rail, four international construction joint ventures and 21 EPB Shields from Herrenknecht have executed one of the most ambitious tunnel projects in the world in Qatar. Read the full story about the record-breaking construction in our case study!
Explore case study