Herrenknecht AR Logo

All Around #7

EVERYTHING FLOWS

 

International championship alliance completes world class metro tunnel project in Doha in record time.

111 KILOMETER IN 26 MONTHS – WORLD RECORD MISSION COMPLETED

Out of nowhere, almost unnoticed underground, an epoch-making structure is created in Doha. With a total of 111 kilometers a top-class metro tunnel project. The protagonists of the prestige project: Qatar Rail, four international construction joint ventures and 21 EPB Shields from Herrenknecht.

 

Together they realize a highly complex, extremely ambitious undertaking that seeks its equal worldwide. After 26 months of tightly directed tunnelling flow, it was successfully completed with the final breakthrough on September 25, 2016.

FLOW³

MULTITASKING IN PERFECTION

 

Precise, on schedule, synchronous: 21 tunnel boring machines were needed to drive the mega project forward on three metro lines. Under the direction of Qatar Rail, four international joint ventures delivered an unprecedented tunnelling rally under enormous time pressure with the highest standards of safety.

 

Follow the tunnel borers on their journey through time. Witness a new benchmark on an international scale: Flow³.

TimelineTBM S-846TBM S-865TBM S-867TBM S-868TBM S-847TBM S-860TBM S-862TBM S-866TBM S-863TBM S-920TBM S-921TBM S-922TBM S-923TBM S-924TBM S-925TBM S-864TBM S-861TBM S-849TBM S-848TBM S-844TBM S-84508.01.2016IntermediateBreakthrough30.12.2015IntermediateBreakthrough24.02.2016IntermediateBreakthrough07.03.2015IntermediateBreakthrough08.02.2016IntermediateBreakthrough29.02.2016IntermediateBreakthrough18.02.2016IntermediateBreakthrough13.02.2016IntermediateBreakthrough28.02.2016IntermediateBreakthrough02.02.2016IntermediateBreakthrough14.11.2015IntermediateBreakthrough08.11.2015IntermediateBreakthrough10.11.2015IntermediateBreakthrough22.11.2016IntermediateBreakthrough26.10.2015IntermediateBreakthrough16.11.2015IntermediateBreakthrough28.10.2015IntermediateBreakthrough25.10.2015IntermediateBreakthrough10.09.2015IntermediateBreakthrough10.10.2015IntermediateBreakthrough13.10.2015IntermediateBreakthrough10.10.2015IntermediateBreakthrough30.08.2015IntermediateBreakthrough30.09.2015IntermediateBreakthrough29.08.2015IntermediateBreakthrough21.07.2015IntermediateBreakthrough26.07.2015IntermediateBreakthrough05.09.2015IntermediateBreakthrough21.09.2015IntermediateBreakthrough04.10.2015IntermediateBreakthrough27.09.2015IntermediateBreakthrough14.10.2015IntermediateBreakthrough25.10.2015IntermediateBreakthrough02.10.2015IntermediateBreakthrough06.10.15IntermediateBreakthrough30.07.2015IntermediateBreakthrough03.06.2015IntermediateBreakthrough24.06.2015IntermediateBreakthrough11.06.2015IntermediateBreakthrough23.06.2015IntermediateBreakthrough23.07.2015IntermediateBreakthrough31.05.2016IntermediateBreakthrough31.01.2015IntermediateBreakthrough04.04.2015IntermediateBreakthrough17.01.2015IntermediateBreakthrough15.04.2015IntermediateBreakthrough26.04.2015IntermediateBreakthrough11.04.2015IntermediateBreakthrough14.04.2015IntermediateBreakthrough25.03.2015IntermediateBreakthrough09.04.2015IntermediateBreakthrough16.06.2015IntermediateBreakthrough01.06.2015IntermediateBreakthrough07.02.2016, S-868FinalBreakthrough12.12.2015, S-847FinalBreakthrough20.03.2016, S-867FinalBreakthrough12.03.2016, S-865FinalBreakthrough31.07.2016, S-864FinalBreakthrough11.07.2016, S-863FinalBreakthrough08.06.2016, S-861FinalBreakthrough01.05.2016, S-925FinalBreakthrough11.05.2016, S-924FinalBreakthrough11.05.2016, S-923FinalBreakthrough12.05.2016, S-922FinalBreakthrough10.09.2016, S-860FinalBreakthrough29.02.2016, S-849FinalBreakthrough27.02.2016, S-848FinalBreakthrough12.12.2015, S-923FinalBreakthrough28.11.2015, S-846FinalBreakthrough29.03.2016, S-844FinalBreakthrough27.03.2016, S-845FinalBreakthrough04.05.2016, S-920FinalBreakthrough19.05.2016, S-921FinalBreakthrough
Accumulated
tunnelling progress

The success in figures

PERFORMANCE PARADE

Maximum machine availability is the basis of peak performance. Together the project participants in Doha managed the feat of delivering an average overall availability of more than 97%.

 

Click through the detailed numbers of the individual TBMs.

 

Overall availability of all TBMs

97.2%

S-860 – Lehwaila (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

96.1

Total tunnelling length: 9,069 m

Maximum advance per week: 269 m

S-861 – Al Wakra (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

98.3

Total tunnelling length: 5,126 m

Maximum advance per week: 216 m

S-862 – Msheireb (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

97.6

Total tunnelling length: 9,130 m

Maximum advance per week: 250 m

S-863 – Doha (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

90.8

Total tunnelling length: 5,074 m

Maximum advance per week: 184 m

S-864 – Al Zubara (Red Line South)

Contractor

Qatari Diar Vinci Construction JV (QDVC)/ GS Engineering & Construction Corp./ Al-Darwish Engineering W.L.L.

96.6

Total tunnelling length: 4,242 m

Maximum advance per week: 190 m

S-865 – Lebretha (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94.1

Total tunnelling length: 7,182 m

Maximum advance per week: 195 m

S-866 – Al Mayeda (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

93.9

Total tunnelling length: 4,157 m

Maximum advance per week: 209 m

S-867 – Al Khor (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94.1

Total tunnelling length: 7,223 m

Maximum advance per week: 209 m

S-868 – Al Bidda (Red Line North)

Contractor

ISG Joint Venture (Salini Impregilo S.p.A./ SK Engineering & Construction Co. Ltd./ Galfar Al Misnad Engineering & Contracting W.L.L.)

94

Total tunnelling length: 4,232 m

Maximum advance per week: 194 m

S-844 – Al Messila (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

96.7

Total tunnelling length: 6,141 m

Maximum advance per week: 210 m

S-845 – Al Sheehaniya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.8

Total tunnelling length: 6,150 m

Maximum advance per week: 213 m

S-846 – Al Rayyan (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.3

Total tunnelling length: 4,082 m

Maximum advance per week: 216 m

S-847 – Al Gharrafa (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

99

Total tunnelling length: 4,090 m

Maximum advance per week: 203 m

S-848 – Leatooriya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

99

Total tunnelling length: 6,454 m

Maximum advance per week: 232 m

S-849 – Lijmailiya (Green Line)

Contractor

 

PORR Bau GmbH/ Saudi Binladin Group Company Ltd./ Hamad Bin Khalid Contracting Co. W.L.L.

98.8

Total tunnelling length: 6,466 m

Maximum advance per week: 283 m

S-920 – Sharq (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.3

Total tunnelling length: 4,371 m

Maximum advance per week: 177 m

S-921 – Lusail (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.1

Total tunnelling length: 4,382 m

Maximum advance per week: 195 m

S-922 – Al Sadd (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.5

Total tunnelling length: 3,557 m

Maximum advance per week: 266 m

S-923 – Al Sailiya (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

98.3

Total tunnelling length: 3,558 m

Maximum advance per week: 180 m

S-924 – Muaither (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.6

Total tunnelling length: 3,725 m

Maximum advance per week: 213 m

S-925 – Al Waab (Gold Line)

Contractor

Aktor S.A./ Larsen & Toubro Limited/ Yapi Merkezi Insaat VE Sanayi Anonim Sirketi/ Sezai Turkes Feyzi Akkaya Marine Construction/ Al Jaber Engineering LLC

99.9

Total tunnelling length: 3,728 m

Maximum advance per week: 201 m

THE PROJECT IN DETAIL

DOHA METRO

Qatar Rail, four international construction joint ventures and 21 EPB Shields from Herrenknecht have executed one of the most ambitious tunnel projects in the world in Qatar. Read the full story about the record-breaking construction in our case study!
Explore case study